BRB, just getting some scratch lotto tickets.
14.3 kw. That's fucking obscene.
And by all rights, the Fintech datacentre is what...small? medium?
GLM again:
One DGX B200 flat-out: 14.3 kW × 24h = ~343 kWh/day ≈ what a typical UK house uses in a month
Datacentre size: a full rack of AI gear like this is ~50–100kW. Classification-wise:
Your average office server closet: 5–20 kW
Small datacentre: <1 MW
Mid-size / enterprise: 1–10 MW
Hyperscale (AWS/Google/Microsoft): 50–500+ MW per campus
Revolut's 56 GPUs ≈ one dense rack or two — well under 1 MW, so firmly "small," and that's exactly why they colocate/rent space ("a US-based service") rather than owning a facility. Self-hosting the GPUs doesn't mean self-hosting the building. You don't put 100kW of fridges in your London office — you rent rack space in a proper colo where the power and cooling already exist.
Enjoy the lotto. If you win, you can buy an eighth of a DGX.
Fuuuuuuuuuck