[–] 1 point 33 minutes ago*

160 m² for 250 kW. 640m² for a single MW if we have perfect conditions. This is for every single MW of compute launched, plus (if we take the ISS as the prime example) 2800(for 120 kW)*8,4=around 24000m² of solar panel for every single MW (even at peak efficiency we are still at 12000m²). The ISS needed 5 launches to deliver and montage their panels. Even if you are doing things very efficently, i doubt that you get away with less than 4 launches for the satellite + solar panels, and that does not include fucking up when doing thousands of launches.